Benedum Hall Transformation

Transformation Timeline and Project Overview

 

Current renovations:

  • The sub-basement, basement, and second floor have been vacated for construction. Those offices moved to other places in Benedum, Posvar, Cathedral of Learning, and the Center for Bioengineering.

  • The Mascaro building is scheduled to be completed by mid-August 2009.

  • The auditorium is scheduled to be completed by mid-July 2009. (Conversion of space into classrooms.)

  • The construction of the Holzman Learning Center (10th floor) is complete. Classes have been held in the center since fall 2008.

 

Upcoming renovations:

  • The new ground floor will be finished in November 2009 and will be converted into classrooms, a café, student organizations, and the library.

  • The sub-basement has a newly added mezzanine level and will become a computing lab and the library stacks. This is scheduled to be completed mid-July 2009.

  • Renovations of the first floor will begin in December 2009 through April 2010.

  • Renovations of the fourth floor will begin January 2010 through late July 2010.

  • Renovations of the fifth floor will begin in July 2010 through December 2010.

  • Phase II (floors 6-12) will begin shortly after.

 

 

Transformation

     

Show Your Support

Name a classroom, lab office, or public area to show your commitment to Pitt Engineering.

You are using a browser that does not support current Web standards. Although this site is viewable in all browsers, it will look much better in a browser that supports web standards.